Rathbone Market – Phase 3

Job Details: Full supply & fit package for John Sisk & Sons.

Situated next to phase 2 we were the only brickwork subcontractor considered for this project that consisted of 3 blocks the tallest being 13 storeys high. Incorporating just shy of 900,00 bricks, 3,500m of masonry support and 915 single leaf lintels, Brickwork to levels 1 & 2 incorporates one brick thick ‘hit & miss’ Flemish bond and half brick thick Flemish bond with 30mm projection on the headers. Our package works commenced in March 2016 and was completed by Sept 16 a total of 27 weeks on site. At the peak of construction, we were employing 40+ bricklayers. Value over £3million

Location
Maud Street E16
Architect
Project Orange
Customer
John Sisk & Sons
Value
£3million+
LOOKING FOR A QUALITY AND AFFORDABLE
CONSTRUCTOR FOR YOUR NEXT PROJECT?
STEVE DOYLE
Willmott Dixon
Supply Chain Manager

D B Ryder have provided brickwork services for Willmott Dixon for over 20 years. Over that period they have consistently delivered premier service on all our projects. Their focus on collaboration, innovation, investing in their people and delivering a quality product, separates them from other companies on our Supply Chain. They are a Supply Chain Partner that our people want to work with.